Project background:
The 20th floor of the communication building was opened up for DC transformation, and the provincial 5G core network and cloud resource pool (the highest class a computer room in the province) were deployed;
Because of the high floor, the risk of load-bearing transformation is high;
Due to the limited area, need to make full use of area to deploy more cabinets;
Project plan:
High voltage DC DPS equipment is deployed in 2N mode, and the standby time is 1 hour;
The device height is 5U to ensure that users have enough space to deploy PC servers;
Make full use of the area of the computer room and reserve expandable space;
Guarantee the high reliability of 5G core network and cloud resource pool services;
Advantages of the scheme:
Fast supply and construction to ensure fast launch service;
High efficiency and reliability of power supply;
It is convenient to expand capacity, support step-by-step investment and improve efficiency;